The California Water Boards' Annual Performance Report - Fiscal Year 2015-16
State Board | Region 1 | Region 2 | Region 3 | Region 4 | Region 5 | Region 6 | Region 7 | Region 8 | Region 9
TARGETS AND RESOURCES: REGION 3 CENTRAL COAST |
|
GROUP: TARGETS AND RESOURCES - REGION 3 |
MEASURE: ALL REGIONAL TARGETS ALL RESOURCES |
Targets Achieved: |
Central Coast Regional Water Board Performance Summary1 | Percentage of Targets Met |
||
Area: 11493 square miles | Budget: $9,759,644 | Staff: 65.2 | |
Permitting 0% • | Inspections 75% • | Others 71% • | |
1Regional Board performance summary statistics show the percentage of targets met. |
Total Maximum Daily Load and Basin Planning | |||||
Program Budget: $1,579,230 | Program Staff: 11.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
Pollutant/Water Body Combinations Addressed | 23 | 31 | 135% • | ||
Total Maximum Daily Loads Adopted | 3 | 2 | 67% • | ||
Basin Plan Amendments Adopted | 0 | 1 | |||
No Regional Considerations Provided | |||||
NPDES Wastewater | |||||
Program Budget: $319,625 | Program Staff: 2.20 | ||||
Target | Actual Achieved | % of Targets Met | |||
Major Individual Permits Issued or Renewed | 6 | 1 | 17% • | ||
Major Individual Facilities Inspected | 15 | 13 | 87% • | ||
Minor Individual Permits Issued or Renewed | 5 | 0 | 0% • | ||
Minor Individual Facilities Inspected | 7 | 6 | 86% • | ||
Minor General Facilities Inspected | 0 | 1 | |||
No Regional Board Considerations Provided | |||||
NPDES Stormwater | |||||
Program Budget: $678,229 | Program Staff: 4.70 | ||||
Target | Actual Achieved | % of Targets Met | |||
Municipal (Phase I/II Inspections) | 11 | 7 | 64% • | ||
Construction Inspections | 20 | 34 | 170% • | ||
Industrial Inspections | 19 | 24 | 126% • | ||
No Regional Considerations Provided | |||||
Waste Discharge to Land - Wastewater | |||||
Program Budget: $1,127,879 | Program Staff: 7.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
Waste Discharge to Land Inspections | 44 | 56 | 127% • | ||
Individual Waste Discharge Requirements Updated | 25 | 7 | 28% • | ||
No Regional Considerations Provided | |||||
Land Disposal | |||||
Program Budget: $370,627 | Program Staff: 2.60 | ||||
Target | Actual Achieved | % of Targets Met | |||
Landfill Individual Permits Updated | 2 | 1 | 50% • | ||
Landfill Inspections | 42 | 36 | 86% • | ||
All Other Individual Permits Updated | 0 | 0 | |||
All Other Inspections | 5 | 1 | 20% • | ||
In response to increasing climate change related disasters like forest fires and floods in California, Central Coast Water Board staff per direction from the Executive Officer developed Conditional Waiver of Waste Discharge Requirements for Disaster Related Emergency Waste Handling and Disposal Within the Central Coast Region (Order No. R3-2016-0001) to facilitate timely emergency waste cleanup and disposal activities to protect public health and water quality. The development of the conditional waiver is consistent with Division of General Services Debris Management Committee recommendations to address disaster related cleanup response needs and is consistent with the development of similar regulatory instruments by Regions 5, 6, 8 and 9. At the time the decision was made to develop the conditional waiver, it was determined that it was a regional priority over the development or update of an individual landfill permit as identified as a FY 15/16 performance target for Region 3. | |||||
Confined Animal Facilities (WDR, NPDES, etc.) | |||||
Program Budget: $0 | Program Staff: 0.00 | ||||
Target | Actual Achieved | % of Targets Met | |||
Confined Animal Facilities Inspections | 0 | 1 | |||
No Regional Considerations Provided | |||||
Timber Harvest (Forestry) | |||||
Program Budget: $0 | Program Staff: 0.00 | ||||
Target | Actual Achieved | % of Targets Met | |||
Timber Harvest Inspections | 0 | 0 | |||
No Regional Considerations Provided | |||||
Enforcement | |||||
Program Budget: $153,257 | Program Staff: 1.00 | ||||
Target | Actual Achieved | % of Targets Met | |||
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery | 100% | 100% | 100% • | ||
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual | 0 | 1 | • | ||
No Regional Board Considerations Provided | |||||
Cleanup | |||||
Program Budget: $998,225 | Program Staff: 5.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
New Department of Defense Sites Into Active Remediation | 0 | 10 | |||
New Cleanup Sites Into Active Remediation | 2 | 2 | 100% • | ||
Cleanup Sites Closed | 8 | 13 | 163% • | ||
New Underground Storage Tank Sites Into Active Remediation | 6 | 1 | 17% • | ||
Underground Storage Tank Sites Projected Closed | 30 | 33 | 110% • | ||
No Regional Considerations Provided | |||||