Colorado River Regional Water Board Performance Summary1
Percentage of Targets Met
Area: 19863 square miles Budget: $4,902,821 Staff: 32
Permitting 60% Inspections 89% Others 75%
1Regional Board performance summary statistics show the percentage of targets met.
 
Total Maximum Daily Load and Basin Planning
Program Budget: $818,357 Program Staff: 6.30
  Target Actual Achieved % of Targets Met
Pollutant/Water Body Combinations Addressed 5 0 0%
Total Maximum Daily Loads Adopted 0 0  
Basin Plan Amendments Adopted 1 1 100%
No Regional Considerations Provided
NPDES Wastewater
Program Budget: $288,946 Program Staff: 1.80
  Target Actual Achieved % of Targets Met
Major Individual Permits Issued or Renewed 1 4 400%
Major Individual Facilities Inspected 4 6 150%
Minor Individual Permits Issued or Renewed 4 0 0%
Minor Individual Facilities Inspected 4 3 75%
Minor General Facilities Inspected 0 0  
No Regional Considerations Provided
NPDES Stormwater
Program Budget: $174,271 Program Staff: 1.20
  Target Actual Achieved % of Targets Met
Municipal (Phase I/II Inspections) 1 1 100%
Construction Inspections 30 30 100%
Industrial Inspections 18 21 117%
No Regional Considerations Provided
Waste Discharge to Land - Wastewater
Program Budget: $539,260 Program Staff: 4.10
  Target Actual Achieved % of Targets Met
Waste Discharge to Land Inspections 56 69 123%
Individual Waste Discharge Requirements Updated 10 11 110%
No Regional Considerations Provided
Land Disposal
Program Budget: $814,045 Program Staff: 5.10
  Target Actual Achieved % of Targets Met
Landfill Individual Permits Updated 3 6 200%
Landfill Inspections 20 22 110%
All Other Individual Permits Updated 4 3 75%
All Other Inspections 20 20 100%
No Regional Considerations Provided
Confined Animal Facilities (WDR, NPDES, etc.)
Program Budget: $61,757 Program Staff: 0.40
  Target Actual Achieved % of Targets Met
Confined Animal Facilities Inspections 8 9 113%
No Regional Considerations Provided
Timber Harvest (Forestry)  
Program Budget: $0 Program Staff: 0.00
  Target Actual Achieved % of Targets Met
Timber Harvest Inspections 0 0  
No Regional Considerations Provided
Enforcement
Program Budget: $24,285 Program Staff: 0.20
  Target Actual Achieved % of Targets Met
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual 0 2        
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery 100% 0% 0%
No Regional Board Considerations Provided
Cleanup
Program Budget: $20,003 Program Staff: 0.10
  Target Actual Achieved % of Targets Met
New Department of Defense Sites Into Active Remediation 2 3 150%
New Cleanup Sites Into Active Remediation 2 4 200%
Cleanup Sites Closed 2 2 100%
New Underground Storage Tank Sites Into Active Remediation 7 8 114%
Underground Storage Tank Sites Projected Closed 7 6 86%
No Regional Considerations Provided