Los Angeles Regional Water Board Performance Summary1
Percentage of Targets Met
Area: 4451 square miles Budget: $35,931,271 Staff: 149
Permitting 60% Inspections 100% Others 100%
1Regional Board performance summary statistics show the percentage of targets met.
 
Total Maximum Daily Load and Basin Planning
Program Budget: $2,852,805 Program Staff: 12.70
  Target Actual Achieved % of Targets Met
Pollutant/Water Body Combinations Addressed 46 46 100%
Total Maximum Daily Loads Adopted 3 3 100%
Basin Plan Amendments Adopted 4 5 125%
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
NPDES Wastewater
Program Budget: $4,489,937 Program Staff: 18.90
  Target Actual Achieved % of Targets Met
Major Individual Permits Issued or Renewed 9 8 89%
Major Individual Facilities Inspected 29 29 100%
Minor Individual Permits Issued or Renewed 12 9 75%
Minor Individual Facilities Inspected 11 11 100%
Minor General Facilities Inspected 32 32 100%
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
NPDES Stormwater
Program Budget: $2,787,867 Program Staff: 14.50
  Target Actual Achieved % of Targets Met
Municipal (Phase I/II Inspections) 0 29  
Construction Inspections 210 422 201%
Industrial Inspections 270 869 322%
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Waste Discharge to Land - Wastewater
Program Budget: $1,315,479 Program Staff: 4.50
  Target Actual Achieved % of Targets Met
Waste Discharge to Land Inspections 20 30 150%
Individual Waste Discharge Requirements Updated 4 3 75%
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Land Disposal
Program Budget: $813,125 Program Staff: 3.50
  Target Actual Achieved % of Targets Met
Landfill Individual Permits Updated 3 4 133%
Landfill Inspections 43 62 144%
All Other Individual Permits Updated 1 1 100%
All Other Inspections 12 11 92%
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Confined Animal Facilities (WDR, NPDES, etc.)  
Program Budget: $0 Program Staff: 0.00
  Target Actual Achieved % of Targets Met
Confined Animal Facilities Inspections 0 0  
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Timber Harvest (Forestry)  
Program Budget: $136,413 Program Staff: 2.10
  Target Actual Achieved % of Targets Met
Timber Harvest Inspections 0 0  
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Enforcement
Program Budget: $1,740,275 Program Staff: 7.70
  Target Actual Achieved % of Targets Met
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery 100% 100% 100%
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual 0 0        
No Regional Board Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.
Cleanup
Program Budget: $6,688,272 Program Staff: 56.00
  Target Actual Achieved % of Targets Met
New Department of Defense Sites Into Active Remediation 0 0  
New Cleanup Sites Into Active Remediation 10 13 130%
Cleanup Sites Closed 12 22 183%
New Underground Storage Tank Sites Into Active Remediation 10 16 160%
Underground Storage Tank Sites Projected Closed 100 140 140%
No Regional Considerations Provided
Please see Region 4's Fact Sheet for a more detailed overview of the program and accomplishments.