Lahontan Regional Water Board Performance Summary1
Percentage of Targets Met
Area: 32792 square miles Budget: $17,712,855 Staff: 62.8
Permitting 50% Inspections 90% Others 75%
1Regional Board performance summary statistics show the percentage of targets met.
 
Total Maximum Daily Load and Basin Planning
Program Budget: $737,321 Program Staff: 5.50
  Target Actual Achieved % of Targets Met
Pollutant/Water Body Combinations Addressed 0 0  
Total Maximum Daily Loads Adopted 0 0  
Basin Plan Amendments Adopted 0 0  
Please see Region 6's Basin Planning fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
NPDES Wastewater
Program Budget: $208,457 Program Staff: 1.20
  Target Actual Achieved % of Targets Met
Major Individual Permits Issued or Renewed 0 0  
Major Individual Facilities Inspected 1 2 200%
Minor Individual Permits Issued or Renewed 2 1 50%
Minor Individual Facilities Inspected 2 2 100%
Minor General Facilities Inspected 0 0  
Please see Region 6's NPDES Wastewater fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
NPDES Stormwater
Program Budget: $330,374 Program Staff: 2.00
  Target Actual Achieved % of Targets Met
Municipal (Phase I/II Inspections) 4 3 75%
Construction Inspections 34 64 188%
Industrial Inspections 10 16 160%
Please see Region 6's Stormwater fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Waste Discharge to Land - Wastewater
Program Budget: $1,940,591 Program Staff: 7.70
  Target Actual Achieved % of Targets Met
Waste Discharge to Land Inspections 36 42 117%
Individual Waste Discharge Requirements Updated 2 3 150%
Please see Region 6's Waste Discharge to Land fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Land Disposal
Program Budget: $875,378 Program Staff: 3.20
  Target Actual Achieved % of Targets Met
Landfill Individual Permits Updated 1 1 100%
Land Fill Inspections 12 16 133%
All Other Individual Permits Updated 1 0 0%
All Other Inspections 11 26 236%
Please see Region 6's Land Disposal fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Confined Animal Facilities (WDR, NPDES, etc.)
Program Budget: $0 Program Staff: 0.00
  Target Actual Achieved % of Targets Met
Confined Animal Facilities Inspections 3 6 200%
No Regional Considerations Provided
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Timber Harvest
Program Budget: $927,575 Program Staff: 5.40
  Target Actual Achieved % of Targets Met
Timber Harvest Inspections 20 29 145%
Please see Region 6's Timber Harvest fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Enforcement
Program Budget: $509,004 Program Staff: 1.90
  Target Actual Achieved % of Targets Met
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery 100% 100% 100%
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual 0 0        
Please see Region 6's Enforcement fact sheet for a more detailed overview of the program and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.
Cleanup
Program Budget: $3,265,654 Program Staff: 7.50
  Target Actual Achieved % of Targets Met
New Department of Defense Sites Into Active Remediation 0 0  
New Cleanup Sites Into Active Remediation 0 0  
Cleanup Sites Closed 5 3 60%
New Underground Storage Sites Into Active Remediation 0 0  
Underground Storage Tank Sites Projected Closed 18 22 122%
Please see Region 6's Cleanup and Department of Defense fact sheets for a more detailed overview of those programs and accomplishments.
Please see Region 6's Fact Sheets for a more detailed overview of the program and accomplishments.