The California Water Boards' Annual Performance Report - Fiscal Year 2016-17
State Board | Region 1 | Region 2 | Region 3 | Region 4 | Region 5 | Region 6 | Region 7 | Region 8 | Region 9
TARGETS AND RESOURCES: REGION 3 CENTRAL COAST |
GROUP: TARGETS AND RESOURCES - REGION 3 |
MEASURE: ALL REGIONAL TARGETS ALL RESOURCES |
Targets Achieved: |
Central Coast Regional Water Board Performance Summary1 | Percentage of Targets Met |
||
Area: 11493 square miles | Budget: $15,355,032 | Staff: 68.2 | |
Permitting 0% • | Inspections 60% • | Others 50% • | |
1Regional Board performance summary statistics show the percentage of targets met. |
Total Maximum Daily Load and Basin Planning | |||||
Program Budget: $2,557,602 | Program Staff: 11.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
Pollutant/Water Body Combinations Addressed | 9 | 0 | 0% • | ||
Total Maximum Daily Loads Adopted | 1 | 0 | 0% • | ||
Basin Plan Amendments Adopted | 2 | 1 | 50% • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
NPDES Wastewater | |||||
Program Budget: $585,034 | Program Staff: 2.20 | ||||
Target | Actual Achieved | % of Targets Met | |||
Major Individual Permits Issued or Renewed | 6 | 0 | 0% • | ||
Major Individual Facilities Inspected | 15 | 4 | 27% • | ||
Minor Individual Permits Issued or Renewed | 5 | 0 | 0% • | ||
Minor Individual Facilities Inspected | 7 | 1 | 14% • | ||
Minor General Facilities Inspected | 0 | 1 | |||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
NPDES Stormwater | |||||
Program Budget: $955,411 | Program Staff: 4.70 | ||||
Target | Actual Achieved | % of Targets Met | |||
Municipal (Phase I/II Inspections) | 6 | 5 | 83% • | ||
Construction Inspections | 23 | 34 | 148% • | ||
Industrial Inspections | 26 | 42 | 162% • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Waste Discharge to Land - Wastewater | |||||
Program Budget: $1,666,710 | Program Staff: 7.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
Waste Discharge to Land Inspections | 54 | 35 | 65% • | ||
Individual Waste Discharge Requirements Updated | 23 | 4 | 17% • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Land Disposal | |||||
Program Budget: $557,584 | Program Staff: 2.60 | ||||
Target | Actual Achieved | % of Targets Met | |||
Landfill Individual Permits Updated | 1 | 0 | 0% • | ||
Landfill Inspections | 42 | 51 | 121% • | ||
All Other Individual Permits Updated | 0 | 0 | |||
All Other Inspections | 17 | 4 | 24% • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Confined Animal Facilities (WDR, NPDES, etc.) | |||||
Program Budget: $0 | Program Staff: 0.00 | ||||
Target | Actual Achieved | % of Targets Met | |||
Confined Animal Facilities Inspections | 3 | 1 | 33% • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Timber Harvest (Forestry) | |||||
Program Budget: $289,987 | Program Staff: 1.80 | ||||
Target | Actual Achieved | % of Targets Met | |||
Timber Harvest Inspections | 0 | 0 | |||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Enforcement | |||||
Program Budget: $243,512 | Program Staff: 1.00 | ||||
Target | Actual Achieved | % of Targets Met | |||
Class 1 Priority Violations will Result in Formal Enforcement or an Investigative Order Pursuant to Water Code Section 13267 within 18 Months of Discovery | 100% | 100% | 100% • | ||
Facilities with Over $12,000 in MMPs (4 or More Violations) Not Assessed within 18 Months of Accrual | 0 | 1 | • | ||
No Regional Board Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||
Cleanup | |||||
Program Budget: $2,197,714 | Program Staff: 11.70 | ||||
Target | Actual Achieved | % of Targets Met | |||
New Department of Defense Sites Into Active Remediation | 0 | 3 | |||
New Cleanup Sites Into Active Remediation | 2 | 12 | 600% • | ||
Cleanup Sites Closed | 10 | 10 | 100% • | ||
New Underground Storage Tank Sites Into Active Remediation | 8 | 3 | 38% • | ||
Underground Storage Tank Sites Projected Closed | 25 | 25 | 100% • | ||
No Regional Considerations Provided | |||||
Please see Region 3's Fact Sheet for a more detailed overview of the program and accomplishments. | |||||