On July 24, 2014 the Water Board issued a 13267 Order requiring Crystal Geyser to investigate groundwater quality and process wastewater impacts. CG Roxane LLC has been discharging process wastewater to three onsite ponds for at least 10 years. Based upon Water Board staff’s observations and sample results the Facility’s wastewater discharge facilities present a significant risk of discharging pollutants at concentrations that could adversely affect the quality and beneficial uses of the surface waters and groundwater at and near the Facility.
The required site investigation and technical reports are necessary to further understand the Facility’s wastewater characteristics, and to assess the impact(s) upon receiving water (surface waters and groundwater) quality and beneficial uses due to current and past waste discharge practices at the Facility. The information obtained during the investigations will also be used to determine compliance with the state water quality protection laws and regulations, and the need, if any, for corrective actions in the future.
Lahontan has developed Waste Discharge Requirements for ongoing waste discharges from the bottling facility which are on the January 11, 2016 Board Meeting Agenda.
Related Documents-Site Investigation
- Technical Memorandum on Arsenic Distribution
- Phase 3 Report - Lahontan Comments Regarding Phase 3 Report
- Phase 3 Report - CGR Response to Comments
- Phase 3 Report Revised
- Amended 13267 Order AO2
- Notice of Public Meeting scheduled for December 2, 2016: Investigation and permitting for Crystal Geyser's Olancha and Cabin Bar Ranch Spring Water Bottling Facilities
- Crystal Geyser Olancha 13267 Letter R6V 2014-00063
- Site Investigation Workplan October 2014
- Supplemental Site Investigation Workplan
- Conditional Acceptance of Site Investigation Workplan
- Phase 1 Site Investigation Report
- CGR Olancha Amended 13267 Order R6V 2014-00631A1
- Phase 2 Site Investigation Workplan
- Phase 2 Site Investigation Workplan RWQCB Comments
- Phase 2 Site Investigation Report
- Phase 3 Site Investigation Workplan RWQCB Comments
- Revised Additional Site Investigation Workplan, Geosyntech, July 13, 2016
- Phase 3 Site Investigation Report, October 20, 2016
- Water Board Comments on Phase 3 Investigation Report
- Phase 4 Investigation Workplan
Related Documents-Permitting
- Crystal Geyser Olancha Waste Discharge Requirements and Monitoring/Reporting Program, adopted January 11, 2017
- CGR Olancha Revised Report of Waste Discharge
- CGR Olancha Facility Waste Generation and Discharge Systems Report
- CGR Olancha Waste Generation and Discharge Systems Report RWQCB comments
- Response to RWQCB comments on Facility Waste Generation and Discharge Systems Report
- CGR Olancha-Notice of Violation and Requirement for Report of Waste Discharge
- CGR Olancha Report of Waste Discharge
- CGR Olancha Report of Waste Discharge RWQCB comments