Sierra Pacific Industries - Arcata Division Sawmill Information
SIERRA PACIFIC INDUSTRIES PLANS SAWMILL CLEANUPSierra Pacific Industries (SPI), in conjunction with the North Coast Regional
Water Quality Board (NCRWQCB), is currently conducting several environmental
studies in and around its Arcata Division sawmill located at 2593 New Navy Base
Road, Arcata, California.
General Information
- Fact Sheet - Environmental Activities Update - June 2003
- Public Participation Plan - May 9, 2003
- Fact Sheet - October, 2004
Reports
- Priority Pollutant-Dioxin Study April 30, 2003
- FIRST QUARTER 2003 GROUNDWATER MONITORING REPORT - June 9, 2003
- PLYWOOD COVERED DITCH INVESTIGATION REPORT - June 9, 2003
- INTERIM REMEDIAL MEASURES REPORT - June 10, 2003
- WASTE OIL UNDERGROUND STORAGE TANK INVESTIGATION AND CLOSURE REPORT - June 10, 2003
- FORMER TEEPEE BURNER INVESTIGATION REPORT - July 21, 2003
- SECOND QUARTER 2003 GROUNDWATER MONITORING REPORT August 7, 2003
- RETENTION POND, DITCHES
6 AND 7 AND TRUCK SCALE SUMP
DISCHARGE POINT INVESTIGATION REPORT - October 21, 2003 - Third Quarter 2003 Groundwater Monitoring Report - November 3, 2003
- Baseline Human Health Risk Assessment of On-site Soil and Groundwater - November 20, 2003
- Final Feasibility Study
for Remediation of Wood Surface Protection Chemicals - December 1, 2003
- Report on Interim Remedial Measures: Source Area Removal - December 1, 2003
- Fourth Quarter 2003 Groundwater Monitoring Report - January 22, 2004
- NPDES Self-Monitoring Annual Summary Report for Year 2003 - February 24, 2004
- BURIED DRUM INVESTIGATION REPORT - March 15, 2004
- FORMER WASTE OIL UNDERGROUND STORAGE TANK ADDITIONAL INVESTIGATION REPORT - March 30, 2004
- Groundwater Monitoring and Progress Report First Quarter 2004 - April 30, 2004
- PLYWOOD COVERED DITCH SOIL EXCAVATION REPORT - March 30, 2004
- Monitoring Wells MW-20 and MW-21 Installation and Soil Sampling Report - April 7, 2004
- Addendum to Report on Interim Remedial Measures - April 29, 2004
- 2003–2004 Annual Report for Storm Water Discharges Associated with Industrial Activities - June 30, 2004
- Groundwater Monitoring and Progress Report Second Quarter 2004 - July 27, 2004
- Groundwater Monitoring and Progress Report Third Quarter 2004 - October 15, 2004
- Ditch 6 Soil and Grab Groundwater Sampling Report - October 20, 2004
- Fourth Quarter 2004 Groundwater Monitoring Report - January 26, 2005
- NPDES Self-Monitoring Annual Summary Report for Year 2004 - February 24, 2005
- Groundwater Monitoring and Progress Report - March 2005
- Groundwater Monitoring and Progress Report - October 28, 2005
- Site Management Plan - November 8, 2005
- Drainage Ditch 7 Soil Removal Report - January 18, 2006
- Truck Shop Area Monitoring Wells and Piezometers Installation and Sampling Report - January 27, 2006
- Groundwater Monitoring and Progress Report March 2006 Sampling Event - May 2006
- 2005 Annual Report for Storm Water Discharges Associated with Industrial Activities - June 20, 2006
- Results of Pilot Study of Proposed Remedial Action - July 2006
- Groundwater Monitoring and Progress Report August 2006 Sampling Event - October 2006
- Proposed Monitoring and Reporting Program Arcata Division Sawmill - February 22, 2007
- Scoping Ecological and Off-Site
Human Health Risk Assessment - Revised July 23, 2007
Note: Originally created September 8, 2004, Revised in September 2006. This is the latest revision.